Maintenance on Peachtree City’s cart path tunnels is scheduled to begin next week.

The city’s contractor will be doing work that requires several path tunnels to close temporarily.  Work will be performed at night, with setup at 8 p.m., tunnel closure at 9 p.m., and the tunnel reopening each morning at about 4 a.m.

The current schedule is:

Kelly Drive, July 25-26

Ethan Allen, July 27-29

Best Buy, Aug. 1-2

McDonald’s, Aug. 3-5

Ardenlee, Aug. 8-9

Georgian Parkway, Aug. 10-12

 