The extension of TDK Boulevard, which would provide another transportation
link between Peachtree City and Coweta County, likely will be getting a redesign
on the Fayette side.
The current design for the road has the extension passing along the northern
border of the airport, but that would encroach into the airport's runway
safety area. FAA officials indicated that could cause a problem in the future,
so Peachtree City is making plans to re-route the initial part of the road.
Currently, TDK dead-ends just past Dividend Drive in the city's industrial
park area.
Falcon Field's runway safety area extends 1,000 feet from the end of
the runway and is designed to give aircraft extra room if problems arise
during takeoff or landing.
The city's airport authority met Wednesday night, approving a $10,000
payment to the city to help fund the redesign process. Officials plan to
use two existing golf holes at Planterra Ridge golf club, which is adjacent
to Falcon Field, so the road could be routed around the airport's runway
safety area.
The holes will likely be relocated on undeveloped land nearby that must
be purchased by the city, officials said.
The city council is expected to take up the issue of redesigning the TDK
extension at its meeting Thursday.
The $10,000 from the airport authority will come out of its general fund,
said Chairwoman Cathy Nelmes.
Land set aside for the proposed new reservoir for Fayette County, Lake McIntosh,
is also in the area and factors in to the design of the road. The county
hasn't received permission from regulatory agencies to build the lake
yet, however.
Also a factor is Line Creek, which forms a natural barrier between Fayette
and Coweta counties, thus requiring a bridge for the project also.
Falcon Field Airport Manager John Crosby noted that the county has committed
to paving the road with its crews, but "they just don't know where."
The design process has been left up to Peachtree City and until he resigned
recently to take another job, the project was handled by City Engineer Troy
Besseche.
As late as June of this year, officials estimated the project would be complete







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…