Senoia city administrator Murray
McAfee huddled with contractors and officials from Georgia Rural Development
yesterday to try and get a handle on when the city's sewer system
will be completed.
For the last few months, the
East Coweta town has been a sea of mud as sewer contractors lay pipes
and build lift stations. During Monday's City Council meeting, McAfee
told the council that nearly 35 percent of the pipes had been laid in
the city, while nearly 83 percent of the spray field construction was
complete.
"We're having a frank
discussion about when we can expect to see this project completed,"
he said.
The project reminds on schedule,
as far as cost goes, but McAfee said the progress has been hindered by
some very large, unforeseen obstacles. The first line that was supposed
to be completed was the Martinwood subdivision, just off Rockaway Road.
But as the contractors have
discovered, the area is laden with rock, and they're having to rethink
their approach to the area.
"They're talking
about running a line in a different area to try and get away from all
the rock they have run into," McAfee said.
While the project has run into
problems in Martinwood, the news from other areas of the city is far more
positive. McAfee said the contractors have had success with running the
Clark Street line, and that line could be hooked up in just over a month.
The city administrator hoped
to come out of yesterday's meeting with a better feel for the timeline
on hooking up other areas of the city. The city's ordinance gives
residents 90 days to hook up to the system, after it's completed
in their neighborhood.
After the 90 days, residents
will have to pay a tap-on fee.