The first tangible proof of
the county's new judicial center occured this week as demolition
began on the old Quality Foods shopping center.
Once the demolition and clearing
is completed, Coweta County expects to stage a groundbreaking for the
judicial center in April.
Choate Construction won the
contract for the $40 million complex, which is being funded through a
Special Purpose Local Option Sales Tax.
Officials estimate the center
will open 18 months from ground breaking.
Some of the specifics of the
new complex include:
- Main courts building
- 129,000 sq. ft.
- Juvenile courts building
- 30,000 sq. ft.
Coweta County officials said
the current projection shows the complex $1.3 million under budget.
However, officials stressed
there are still some $800,000 in known costs for security and landscape
items coming up, so the project remains under budget even after those
costs are considered.
Building takes architectural
features of the historic courthouse and incorporates them into the new
facade making the facility blend in with the overall appearance of Newnan.
The county has been meticulous,
in fact, about the type of bricks to be used on the exterior of the structure.
For the last few months, the courthouse committee has been bringing brick
samples to the Coweta County Commission meetings.
Chairman Vernon "Mutt"
Hunter has been meticulous about the color red involved in the bricks
and the committee is on the verge of making its final choice.
�







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…