This is the first rate hike
for Fulton County water and sewer customers since January 1, 1997.� Three
public hearings were held in November to present the need for the improvements
and to notify residents of the rate change.
Sewer system tap fees in the
Johns Creek and Big Creek service areas and water system connection fees
for Fulton County customers will increase by 100 percent, also effective
January 1.
The increases are part of the
financing strategy for a $258 million, 2004 through 2006 water and wastewater
capital improvement program (CIP).� A $287 million, 30 year revenue bond
is expected to be issued in the first quarter of 2004.� Ten percent of
the bond amount will be used for debt service reserve and other associated
costs.
In addition to the rate and
fee increases, the program will also be funded through available retained
earnings in the Fulton County Water and Sewer Utility Fund.
Work for the 2004 CIP is expected
to begin in the first quarter of next year, and to be completed by the
end of 2008.� Projects in the CIP are based on a detailed analysis of
the FultonCounty water and sewer infrastructure system in conjunction
with the development of a long-term Strategic Business Plan.