It had been
a while since the Peachtree City Water and Sewerage Authority had had
a meeting. The group convened Monday night and approved the budget for
the capital improvement program for fiscal year 2004 after a summer hiatus.
The total cost
of the projects is estimated to be $6,662,000 and WASA has $6,785,000
left from the bonds they sold. Among the capital improvement programs
scheduled for 2004 are a power generator for the Rockaway plant which
is estimated to cost $250,000 and replacement of a building at Line Creek
that is 32 years old and has leaks and some structural damage, which is
estimated to cost $150,000.
General manager
Larry Turner felt that the replacement needed to be done as lab equipment
inside needed to be protected better and that the staff that worked inside
at all hours of the day also needed a better venue for performing daily
operational tests. Other projects include manhole rehabilitation of the
75 manholes in town for $150,000 and $100,000 for a pond fence near Line
Creek and Stallings Road which will keep vehicles out.
"We have
recently had a problem with what I'd call vandalism," said Turner.
He explained that four-wheelers were driving in the area, which is prohibited,
and that other staff members had seen pick-up truck tracks in the area.
The fence that they would put up in the area would only be able to keep
out vehicles.
Members of
WASA passed the budget for the 2004 capital improvement programs with
the understanding that before any money could be spent on any of these
projects they would have to come before a vote by the authority.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…