The stadium's
old field had worn badly over the years, and did not have sufficient drainage.
The new field covers new grading with a herringbone-patterned drainage
system, six inches of sand, four inches of "root zone" material
(clay, sand and soil mixture), and new sod.
It is also
a part of a number of school system projects that are finishing up for
the new year or about to start through the end of 2003. Other projects
finishing or coming include:
Several projects
at Northgate High School, including work on the stadium homeside concession
stands (nearing completion), new tennis courts (approximately half completed),
and construction of a new gymnasium (which is just starting).
Grantville
Elementary School, beginning soon on U.S. Highway 29 in Grantville (currently
completing permits). The school, which will have a capacity of approximately
500 students, is expandable over time. The school will also be built on
a more traditional design, looking more like a "traditional red brick
school house" and including a "cafetorium" style stage
and cafeteria combination, said Coweta County School System Plant Operations
Director Coy Mills.
Construction
of a new gymnasium at East Coweta Middle School (currently completing
permits and bid returns).
An eight-classroom
expansion at Arnall Middle School (footings poured and construction underway).
Construction
of four new classrooms at Jefferson Parkway Elementary and six new classrooms
at Canongate Elementary School (currently awaiting bid returns).
A multipurpose
building at Western Elementary School (construction underway).
Construction
of the Performing Arts Center on Lower Fayetteville Road. Work is proceeding
on schedule at the site, and is still expected to be completed by February
2004.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…