Commuters and
Peachtree City residents have a month to go before work is complete on
repaving the length of Ga. Highway 74 from I-85 in Fulton County south
to Starr's Mill.
Despite 18
days of rain within the contract period for completing the work, the crews
are on schedule to finish the project by July 23, said Dorothy Daniel,
communications officer with the state Department of Transportation.
"They've
had 18 rain days, but on the days it didn't rain, it's been moving real
well," said Daniel, confirming that another couple of weeks of detail
work like shoring up road shoulders and putting down stripping will extend
the final project finish date to early August.
"Weather
permitting," she added.
To help alleviate
congestion on the already busy Hwy. 74 corridor, the work is being performed
at night, from 7 p.m. to 6 a.m. The work has been particularly frustrating
for drivers within the past week, as the crews are now on the two-lane
stretch of Hwy. 74 below Ga. Highway 54. Closing one lane to all traffic
and rerouting it to a single lane has caused bottlenecks in the early
evenings, especially around the industrial park.
The repaving
is part of the state DOT's regular maintainenance program. Hwy. 74 is
still planned to be four-laned south to Starr's Mill sometime in the future.