Senoia will
turn into a giant construction zone next week as construction finally
starts on the city's sewer system.
The $8.5 million
dollar system will take a year to build and will finally connect some
of the older homes to a sewer system.
City administrator
Murray McAfee said the system will also accommodate the city's growth.
"We've
currently got 900 housing units in the city. In the next five to seven
years, we expect to add an additional 1,200-1,300 homes," he said.
McAfee is meeting
with the construction crews, project managers and city workers on Monday
to finalize strategy for the construction. Residents will first see work
in the Martinwood subdivision. For the last few years, the city has been
spending more than $700 a week to pump out the subdivisions failed septic
system.
"After
that, we'll focus on the older areas of town and move towards the Willow
Dell subdivision," he said.
Money for the
project comes from a series of grants and loans from the state's Rural
Development agency, community development grants and developer contributions.
With the more
than 1,200 homes expected to be built in the next few years, McAfee said
the city will have no problem in paying off the loans.
McAfee said
it is possible that no home will be connected to the sewer until the entire
system is completed, but it's too early in the construction phase to provide
a definitive answer.
Senoia has
been discussing building a sewer system for more than 20 years, and McAfee
is glad the construction phase has finally arrived.
"It's
something we've been working on for a long time," he said.