The Peachtree City Council
voted Thursday to dip into contingency funds to come up with the extra
$18,650 it needs to get the engineering portion of the TDK Boulevard Extension
going again.
Combined with the $17,450
remaining from earlier work on the project, the $36,100 should fully pay
to redraw the plans for the connector road between Fayette and Coweta
counties. Work on the engineering phase has been halted for about two
months while city officials tried to figure out the best way to pay for
a change order requested by the Fayette County government.
The county stands to save
$180,000 in construction costs later this year because the road won't
require as much rock removal. County Commission Chairman Gregg Dunn ad
earlier this week sent a letter to members of the Peachtree City Council
encouraging them to pass some kind of funding fix.
"I want to do all we
can to put this thing to bed," said councilman Dan Tennant before
the vote, which was unanimous at 4-0 with councilman Steve Rapson absent.
"Chairman Dunn's letter made it clear (the county) won't put any
more money into this."
Mayor Steve Brown, a critic
of the road because he says it will further clog traffic on two-lane Georgia
Hwy. 74 South, said he didn't want to "put another dime" into
the project, and asked City Engineer Troy Besseche if there was any chance
the engineering work would still exceed the $36,100 figure.
"We don't anticipate
any more costs," he said, adding that negotiations were ongoing with
right-of-way acquisition involving the county, Pathway Communities and
the owners of the Planterra Ridge golf course.
Brown asked when Besseche
thought the plans would be "on his desk" and he replied "Aug.
1, though I'd probably like a day to look over them one last time."
After that, the contractor
can begin initial work on the road, which will take about a year to complete.
Peachtree City is paying for
the engineering and design work on the project, while the county governments
of both Fayette and Coweta are sharing the construction costs.
City Manager Bernard McMullen
reminded the council that a final $50,000 payment is due from the city
to the Fayette County Commission for its share, but that will be part
of the FY04 budget and won't be due until Dec. 31.