Crews are wrapping
up the actual dredging of Lake Peachtree, with just a small area left
which could be completed today, according to officials.
It will still
take a little while to let the remaining silt dry in the temporary drainage
ponds on Drake Field, county consulting engineer David Jaeger told the
Fayette County Water Committee at its meeting Wednesday morning.
After the silt
dries, it is trucked off-site for final disposal. The contractor will
have to restore Drake Field to its original condition, which will also
take some time, Jaeger added.
The silt has
been drying quicker than the contractor expected, Jaeger said, adding
that there have been few complaints, especially considering how large
the project is.
"It has
gone extremely well," Jaeger said.
Water system
director Tony Parrott said the situation with the temporary road providing
access to Drake Field from Ga. Highway 54 has worked well. There have
been no complaints from Peachtree City or the Georgia Department of Transportation
about the gravel road, Parrott said.
The county
chose a contractor for the project that has used a floating barge system
to excavate the silt from the bottom of the lake, which serves as a drinking
water reservoir. The lake is owned by Peachtree City, but the county has
agreed to dredge the lake periodically because the city allows it to be
used as a reservoir.