Plans for the
extension of TDK Boulevard across Line Creek and into Coweta County are
"90 percent complete" but have sat unfinished since late March
because of a disagreement between Fayette County and Peachtree City over
who should pay for engineering cost overruns.
Construction
of the road as proposed would require the blasting of rock from Line Creek,
a prospect that could cost the county an additional $180,000 but could
be avoided altogether if the design of the bridge is elevated.
But redesigning
the bridge at this stage, city engineer Troy Besseche said, will cost
an additional $63,000, an amount the city has said it simply cannot afford
and will not pay, even though a Feb. 9 financial agreement to build the
road required that the city pay all engineering costs and the county governments
share in the construction costs.
"The county
will have saved $180,000 by having the city pay an additional $63,000,"
said Besseche, who estimated Peachtree City has already shelled out in
excess of $300,000 on the project.
But County
Commissioner Greg Dunn said the added engineering costs are down to $30,000
and doesn't see this as a squabble between Peachtree City and the county.
"We have
a signed intergovernmental agreement with Peachtree City saying they're
going to pay for that engineering," Dunn said.
Dunn said if
Peachtree City has a problem with the agreement, city officials should
have asked to amend the agreement.
The county
asked the city to look into redesigning the bridge so the approaches on
both sides are higher, and thus clear the rock below, Besseche said.
"We told
them what the cost change was, but they said they weren't paying that,"
said Besseche.
Lee Hearn,
Fayette County public works director, said the wording in the contract
between the two governments leaves no doubt to who is responsible.
"In the
intergovernmental agreement, it was clear that they (Peachtree City) were
responsible for all the engineering funding," Hearn said. "It's
just unfortunate it has taken this long to get going on the project."
Peachtree
City has no logical reasons for delaying the extension, Hearn pointed
out, since the city will benefit greatly and is getting a good deal financially.
But in the
meantime, while each side waited for the other to blink, the drawings
have been gathering dust in the engineering department at Peachtree City
Hall for nearly two months. Coweta County engineers, meanwhile, continue
with right-of-way and easement work on its side of Line Creek, Besseche
said.
So far, the
debate over who should ante up has not gone higher than the staff level,
said Colin Halterman, who on Monday returned to his job as head of the
city's public services department after an eight-month stint as acting
city manager.
But the question
of whether or not the city should or can pay the $63,000 will likely be
on the June 5 City Council agenda, he said.
The delay is
a sticky issue for some members of the business community, who see the
Coweta-Fayette link as vital to bringing any new businesses into the industrial
park. Many of Peachtree City's industrial workers live in Coweta, and
traffic conditions on Ga. Highway 54 at rush hour are near gridlock now.
TDK Boulevard
proponents are also eager to have that route open and new commuter habits
established before work is completed on widening Hwy. 54, which is still
about two to three years off.
Some have accused
Mayor Steve Brown of stalling the project. In a letter to County Commission
Chairman Greg Dunn dated April 28, Brown says that the final plans for
the road "will meet the criteria of our agreement. It must be noted
that should you wish to make changes or amend those plans for any reason,
it will be at your expense."
Brown has butted
heads with the Chamber of Commerce and the Peachtree City Development
Authority in recent months and was perceived as an opponent of the extension
in the early going. But city staff say he has no greater role in the present
stalemate.
"Not true,"
said new City Manager Bernard J. McMullen. Besseche said the financial
haggling is what's holding up the road, plain and simple, and not "one
person ... We're trying to do it in a way that it won't waste city funds,"
he said.
While each
side waited for the other to blink, the drawings have been gathering dust
in the engineering department at Peachtree City Hall for nearly two months.
Coweta County engineers, meanwhile, continue with right-of-way and easement
work on its side of Line Creek, Besseche said.
So far, the
debate over who should ante up has not gone higher than the staff level,
said Colin Halterman, who on Monday returned to his job as head of the
city's public services department after an eight-month stint as acting
city manager.
But the question
of whether or not the city should or can pay the $63,000 will likely be
on the June 5 City Council agenda, he said.
The delay is
a sticky issue for some members of the business community, who see the
Coweta-Fayette link as vital to bringing any new businesses into the industrial
park. Many of Peachtree City's industrial workers live in Coweta, and
traffic conditions on Ga. Highway 54 at rush hour are near gridlock now.established
before work is completed on widening Hwy. 54, which is still about two
to three years off.
Some have accused
Mayor Steve Brown of stalling the project. In a letter to County Commission
Chairman Greg Dunn dated April 28, Brown says that the final plans for
the road "will meet the criteria of our agreement. It must be noted
that should you wish to make changes or amend those plans for any reason,
it will be at your expense."
Brown has butted
heads with the Chamber of Commerce and the Peachtree City Development
Authority in recent months and was perceived as an opponent of the extension
in the early going. But city staff say he has no greater role in the present
stalemate.
"Not true,"
said new City Manager Bernard J. McMullen. Besseche said the financial
haggling is what's holding up the road, plain and simple, and not "one
person ... We're trying to do it in a way that it won't waste city funds,"
he said.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…