The dredging
of Lake Peachtree is ahead of schedule, Fayette County consulting engineer
Jim Mallett reported Wednesday to the county's Water Committee.
Although the
contract allows the work to last until September, it appears the project
will be complete much sooner, Mallett said. That means Peachtree City
residents will likely be getting Drake Field back sooner than expected.
The field is
being used to dry out the silt that has been dredged from the lake bottom.
The silt must dry before it is trucked away.
There is a
chance the project may be completed in time for the city's annual July
4th festivities, Mallett said.
The field is
a popular spot for locals who want to watch the city's annual fireworks
show over Lake Peachtree.
The Fayette
County Commission chose to spend more money on the dredging project so
it could avoid having to dramatically lower the level of the lake. The
extra funds were already on hand because of a special account at the water
department which set aside the money.
The lake is
being dredged by two barges that vacuum up the silt from the lake floor
and transport it to Drake Field through a pipe system.
Since the lake
didn't need to be drained for the project, the county avoided possible
environmental problems for the creatures that live in and around the lake.
It also allows the county to have its normal amount of water on hand in
case drought conditions strike.