It looks like
it's going to be a busy summer in Senoia.
The City Council
gave approval Monday night to the bids for the city's sewer system, which
could see up to four construction companies working in the city this year.
The total price
for the system is $8.5 million, which is $2 million more than the city
expected when it estimated the price two years ago.
City engineer
Ben Turnipseed explained the nearly two-year delay in getting the project
to the bid status, plus the increased costs of fuel had increased the
price.
The price also
increased because the city is upping the capacity at the treatment plant
from 70,000 gallons a day to 490,000 gallons a day to cover the city's
growth over the next few years.
The city has
$6.6 million in funding secured for the project, so he explained an additional
$1.9 million would need to be secured from Rural Development to fund the
project.
The agency
has just started its budget for this year, so Turnipseed did not see and
problems in obtaining the additional monies.
Once the funding
is secured, Turnipseed said the city would issue revenue bonds to cover
the project. With additional building projects already on the drawing
board, the additional costs would be covered, he added.
The revenue
bonds will be issued for 40 years, Turnipseed said.
Turnipseed
said construction could start in three months and the timeline for finishing
the project is one year.
The City Council
approved the bids by a unanimous vote.
"It's
been a long time coming," said Councilman Robert Hannah.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…