The Fayetteville City Council
has reached a consensus to move forward with the Southside master plan
after reviewing a report that council members feel is a great improvement
over what could potentially happen on that side of town under current
conditions.
"Compared to what is currently
zoned there, these are great improvements," said Councilman Larry
Dell as he listed some of the various items included in the plan drawn
up by Atlanta consulting firm Urban Collage. Those items include a reduction
in the number of residential units in the area, the formation of a commercial
node at the intersection of Jimmie Mayfield Boulevard and the Ga. Highway
92 connector, and numerous street interconnections and pedestrian paths,
as well as improvements to Perry Creek and considerable amounts of green
space around it.
"If we take no action,
what can happen here in the next 25 years?" said Councilman Glenn
Brewer, adding that a master plan such as this can allow the city to have
some control over what can be developed.
Brewer said that he understands
the feelings of people who have repeatedly talked about Fayetteville's
small-town atmosphere, having come to the city himself for the first time
way back in 1946.
"I was completely against
this plan two years ago," said Councilman Walt White. "I would
have voted against it two months ago."
But his concerns about residential
density and containment of commercial development have been answered to
a significant degree, he added.
The discussion at last Thursday's
council meeting comes on the heels of the fourth and final meeting of
the Southside master plan task force, a group that met for about two months
with Urban Collage representatives in an attempt to find out what all
interested parties landowners, developers and existing residents want
in the area and come up with a solution that benefits everyone.
The task force has faced some
difficult challenges, Mayor Kenneth Steele said, as the Southside master
plan has been discussed for some two years now. "It has not been
rushed," he said.
There was no vote taken at
the last task force meeting. What was sought was a consensus among the
members concerning the report and recommendations Urban Collage gathered
from the task force's input. "I think we have [a consensus],"
Steele said, adding that it is not possible to fully address every issue
at the task force level.
Changes in the city's zoning
ordinance during the past few years have helped the south side of Fayetteville
immensely, Steele said, beginning with an attempt by Wal-Mart in the mid-1990s
to locate a supercenter at Pine Trail, on the north end of town near where
the Uptown Square shopping center currently sits. That led to the development
of Fayette Pavilion, and a series of zoning changes that restrict further
"big box" development, Steele said.
"Wal-Mart could have located
on the south side under the zoning at that time," said Steele. "Now
you cannot have any big-box retail on the south side."
Steele said that the recommended
establishment of commercial nodes in such locations as the corner of Hwy.
92 and Jimmie Mayfield is preferable to long strips of commercial development
such as those already in existence on Hwy. 85 north. These are complemented
in the Southside plan by open space, ample buffers and step-down zoning,
he added.
The townhouse zoning now available
in the area was split into a couple of locations. Steele noted that the
townhouse area next to Kingswood has been reduced from a possible 120-plus
units to about 48.
The Southside master plan,
in the works for about two years, now consists of 267.2 acres of land
on the south edge of Fayetteville, encompassing portions of Ga. Highway
85, the Ga. Highway 92 connector, Jimmie Mayfield Boulevard and Bradley
Drive. With the exception of a few residences and the Ingles supermarket
on Hwy. 92, this land is still mostly undeveloped.
The site currently includes
97 acres of commercially zoned land and 170.2 acres of residential zoning,
with 21.3 acres of that zoned for townhomes and the rest for single-family
houses. The 53.2-acre Simpson tract is in unincorporated Fayette County,
zoned residential-agricultural.
The task force was formed early
in the fall after a large number of residents in the area came to the
City Council with concerns about proposed development in the area, specifically
from previous Southside master plan proposals. The council tabled all
action relating to the master plan for 60 days, then for an additional
month when last week's final task force meeting became necessary.
The final master plan includes
a land use plan, a conceptual site plan displaying potential development
patterns and a development agreement between the city and the relevant
property owners and developers. It calls for 124.5 total commercial acres,
19 total office and institutional acres, 109.2 total residential acres,
and 14.5 acres of open space.
Commercial property under the
plan is consolidated along Hwy. 85 and at the corner of Hwy. 92 and Jimmie
Mayfield (long-term plans include extending the connector from Jimmie
Mayfield to Jeff Davis Drive), and a small office-institutional node is
suggested at the corner of Jimmie Mayfield and Bradley Drive.
The rest is residential land,
bisected by a 300-foot greenway along Perry Creek north of the Hwy. 92
connector. The plan includes three significant open spaces: a 4.8-acre
parcel on the northwest corner of Bradley and Jimmie Mayfield; a parcel
of 3-plus acres to the west of Jimmie Mayfield at the city limits; and
2-plus acres on either side of Perry Creek north of the Hwy. 92 connector.
The proposed pedestrian paths
literally wrap around the entire Southside master plan, running through
the large greenway along Perry Creek and along the southern edge of the
site, as well as north across Bradley Drive where a portion of the proposed
townhomes would sit. At the westernmost portion of the tract, the proposed
Publix shopping center, which would have an access point on Hwy. 85, is
also accessible via a series of interconnected streets from elsewhere
in the section north of Hwy. 92, giving accessibility between various
residential and commercial sites without venturing onto the highway.
According to the report, 97
acres of commercial land currently exist within the city with the ability
to accommodate about 550,000 square feet of commercial space. Also, the
Fayetteville Towne Center shopping center across Hwy. 85 has set a precedent
that forced the task force to assume the probable county rezoning and
commercial development of the Simpson tract, which would bring the entire
commercial area to about 120 acres and some 650,000 square feet of total
building area, the report stated.
The master plan does not decrease
the total acreage of commercially zoned land, but it relocates commercial
zones to create a node at Jimmie Mayfield and Hwy. 92, "rather than
a sprawling mass of commercial buildings along Jimmie Mayfield and Bradley
Drive," the report said, and the master plan and accompanying development
agreement would allow the city to regulate the size, type and character
of commercial buildings "to create more of a neighborhood/village-oriented
commercial node rather than a regional marketplace."
Representatives Urban Collage
briefly reviewed what was accomplished by the 22-member task force during
four long evening meetings the past two months. They emphasized the four
key objectives outlined in the report: minimizing the impact of commercial
zoning on residential areas; limiting high-density housing to specific
areas; developing a meaningful open space; and encouraging development
north and south of the Hwy. 92 connector to be self-contained with interconnected
streets and paths.
Stan Harvey of Urban Collage
noted that Fayetteville has some of the best controls in place for development
of any municipality in metro Atlanta, and added that establishing specific
parameters at the beginning of the development process, as the task force
set out to do, is very important.
A representative of the Chanticleer
subdivision said that his community is split on the issue of commercial
development on the east side of Jimmie Mayfield. Some want no commercial
activity on that site, while others can live with it and understand why
it is recommended there, he said.
Kent Rose of Concordia Properties,
one of the potential developers of the Southside master plan, said that
this is the first time he has been involved in a process like what the
task force undertook. He expressed his understanding that everyone involved
must give up something to work out the necessary compromise, and that
includes an estimated 25-percent loss of residential density for his company.
But he added that he saw a number of strengths in the proposed plan.
A representative of the Kingswood
subdivision noted several positive points, such as the work done around
Perry Creek, the 60-40 impervious surface ratio, the proposed bikepaths
and general park-like atmosphere. The community is concerned about the
townhouse zoning, although pleased with the reduced number of units, noting
that it is a four-zone step-down from their adjacent homes. He said that
having R-22 zoning with half-acre lots next door would still be a two-zone
step, but that would be more acceptable.
Other subdivision residents
share concerns about commercial development on the eastern edge of the
site. A Wyngate representative said that her community would "ideally"
like to not see any there, "but we understand that it's not an ideal
world." She said that she would like to see residential development
between Wyngate and any commercial site (Steele noted that such a development
is already in the works), and that there not be any vehicular access between
the two subdivisions if that happens.
Under the proposed master plan,
Chanticleer and Wyngate would be separated from the commercial node by
a tract that John Wieland Homes is now proposing for half-acre residential
lots. That plan is currently before the city's Planning and Zoning Commission.
Another resident spoke about
the possibility of changes being made during the development process and
what can be done to prevent that. Dell suggested that he take a look at
the development agreements for the Village master plan next to Fayette
County High School, saying that in those plans, everything is tied down
and every detail is concrete.
Back
to News Home Page |







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…