To help fund
approximately $635,000 of capital projects that need immediate attention,
the Peachtree City Council has shifted some funds around in its budget.
Most of that
total $494,943 is related to the widening of Ga. Highway 54 West, and
the city hadn't planned to spend most of those funds until next year.
But the funds will be needed soon, and the council decided to fund them
through its bricks and mortar financing program.
Another project
included in the final total is the renovation of the Neely Fire Station,
a project that has been cut drastically but was still characterized as
a necessity by city staff. Council also elected to take the additional
$96,000 for the project out of its bricks and mortar program. The total
project will cost $296,000, but that price was less than the original
estimate from the architect on the project, noted Finance Director Paul
Salvatore.
The projects
related to the highway widening include an additional $229,000 for relocating
utilities in the corridor, $105,000 for a grant for culverts at the bridge
over the CSX railroad track, $35,000 for bridge enhancements to add a
cart path bridge, $60,000 for new traffic signal poles and $50,000 for
sidewalks along the highway.
The bricks
and mortar funds council shifted for the highway projects and Neely station
renovations were originally tabbed for several other projects in 2004,
including a satellite auto shop facility ($228,750) and the facility buildout
plan for the public works building ($234,532).
The auto shop
facility is crucial since employees are now servicing vehicles such as
fire trucks outside in the cold, said Mayor Steve Brown.
Back
to News Home Page | Back
to the top of the page







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…