A rendering
of the proposed location of the Lake McIntosh reservoir between Coweta
and Fayette counties shows the lake will be adjacent to the McIntosh Estates
subdivision in east Coweta.
The rendering
was displayed at a public information meeting about the project Tuesday
evening in Fayetteville. If Fayette County gets the necessary federal
and state permits to build the 650-acre lake, it will provide approximately
8 million gallons of drinking water a day.
Construction
of the lake will take between two and three years from the time work begins
until the lake is filled, said Tommy Craig, an environmental attorney
from Covington who has coordinated the project for the county.
Craig said
he felt confident the project will get the go-ahead, although the process
of seeking the permits will likely be difficult at times. Although the
project disturbs a significant amount of wetlands, the other two alternatives
studied by the county would impact larger wetland areas, he said.
With an estimated
population of over 233,000 people in 2030, the county figures it will
need a daily water supply of 31.3 million gallons, Craig explained.
When the county's
future water needs were tabulated, several current water sources were
deemed to be unreliable because of drought conditions, Craig said. Line
Creek and Whitewater Creek, which combine for a capacity of 4.6 million
gallons a day, and groundwater wells which can produce up to 4.33 million
gallons a day, fell into that category.
"This
is about making our community drought-proof," Craig said.
The county
also cannot count on purchasing up to 4 million gallons of water a day
from the City of Atlanta because that contract expires next year and the
cost could increase dramatically, Craig added.
The county
already owns the land for the project, which has been on the drawing board
since the early 1970s. County leaders later decided to build the Lake
Horton reservoir first.
Craig said
the Lake McIntosh plan has taken a while because of the need to compile
566 acres of land in other locations for wetland restoration, enhancement
and preservation purposes.
Those properties
were purchased with conservation easements that will last into perpetuity,
Craig added. The idea is to take the farmland and turn it back into habitat
for wildlife, he said.
The county's
plan involves damming up Line Creek to create the lake. The dam will be
located west of Dividend Drive and north of Kelly Drive in Peachtree City.
There are no
federally protected species over six miles downstream from the proposed
dam, Craig said. The project will impact a historic site which will be
removed from the area and either displayed locally or sent to the University
of Georgia, Craig said.
Craig declined
to disclose the location of the historic site because it could encourage
others to loot the site before it can be properly excavated, he said.
The county's
plan also calls for a 150-foot buffer protection area on either side of
streams and tributaries that feed into Line Creek to keep runoff and sediment
from entering the lake. This buffer would also extend around the perimeter
of Lake McIntosh, Craig said.
Dennis Chase
of the Line Creek Association questioned how the buffer area would be
enforced, particularly since some of the streams are in Coweta County,
which is outside of the Fayette County Commission's jurisdiction. The
Georgia Environmental Protection Division is ineffective in such matters,
Chase said.
Craig replied
that the Georgia Department of Community Affairs has employees to "police"
governmental compliance and can revoke their "qualified local government"
status, which affects a government's eligibility for grants, among other
things.
"There
are negative economic sanctions," Craig said.
Fayette County
will be aggressive in fighting runoff and sediment problems since they
can take away from the capacity of the lake, Craig said.
"We are
going to be real concerned about the water quality of this lake,"
Craig said.
The county
considered two other sites for the reservoir, one at the north end of
Whitewater Creek and one at the south end. The northern site was not fully
investigated since it would affect a large number of existing homes, which
would make the project much more expensive, Craig said.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…