the city of Senoia will put out a bid proposal for the second and final
phase of its sewer system.
City administrator
Murray McAfee said the city has obtained all but four of the easements
needed for the system.
If the city
needs to go through condemnation procedures to get the final easements,
McAfee said the process would be completed in time to bid the project
in November.
The city is
getting ready to embark on building phase two of its municipal sewer system.
The price tag for the project is pegged at $6.1 million.
The phase will
complete sewer connections in the heart of the east Coweta city, starting
with Main Street, McAfee said.
Of course,
there are some areas that receive priority, such as the Martinwood subdivision.
"That
will definitely be high on the list," he said.
The city is
building the project with a combination of loans and grants. Rural Development
of Georgia is loaning the city nearly $3.5 million.
The city had
hoped to start construction in June, but McAfee said construction should
start in early 2003 and completed in 2004.
Sewer in the
city has been discussed for more than a decade and McAfee is relieved
to see the project almost ready for construction.