Responding
to outrage from southside Atlanta commuters, the Georgia Department of
Transportation has changed its work schedule for lane closings due to
improvements slated for both sides of I-85 between Flat Shoals Road and
Riverdale Road in south Fulton County.
The DOT's original
plan was to have lane closures beginning at 9 a.m. weekdays and lasting
through 3:30 p.m. The new schedule released Wednesday, however, has only
single lane closures planned during the daytime to help lighten the load
on southside commuters.
Officials now
plan to bunch the work in from 9 p.m. to 5 a.m. Tuesdays through Thursdays
and from 9 p.m. to 10 a.m. Fridays through Saturdays.
"Motorists
are not likely to see daytime work in this section for the first few weeks
of the project," said Steve Henry, DOT Metro District Engineer.
When weekday
lane closures are needed, they will be limited to one lane at a time and
for short distances only, Henry said.
"At every
opportunity, the Georgia Department of Transportation attempts to minimize
the inconvenience on motorists caused by construction work," Henry
said.
The initial
construction will involve minor work such as guard rail installation,
drainage adjustments and shoulder paving, according to the DOT. This work
is typically slated for the later stages of such a project, officials
said.
Construction
crews began work on the 5.11-mile section of road with minimal delays;
recorded backups were no more than one-eighth of a mile long, the DOT
said.
The original
construction schedule was sprung on commuters with little warning Tuesday
as DOT released information about the project to news media.
Back
to News Home Page |







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…