Before Ga.
Highway 54 West is widened to four lanes in Peachtree City, it will cost
hundreds of thousands of dollars to relocate utilities currently in the
area.
Estimated costs
to relocate water, sewer and phone lines are in the neighborhood of $700,000
total, according to the Georgia Department of Transportation. Burying
power lines, however, would cost $1.2 million according to early estimates.
Peachtree City
Mayor Steve Brown hopes to get utility representatives together at a meeting
soon to begin planning the timeline for relocating the pipes and wires.
He also hopes to find money for burying the power lines, which would be
an aesthetic improvement for the area, he added.
The road, once
widened, will have a grassy median in the center that city officials hope
to landscape after completion. The city already plans to use $600,000
in funds from an ARC grant to build a cart path bridge over the highway
near the former entrance to the Wynnmeade subdivision.
Also, the DOT
has chipped in money to help fund the "cloverleaf" design cart
path bridge that will span the current CSX railroad bridge after it is
also widened. The design will allow residents on the western boundary
of Peachtree City to cross the railroad tracks on their golf carts, a
feat that can currently only be done to the far south at the tunnel under
Kelly Drive or the far north at the cart path bridge over Ga. Highway
74 north near Oak Manor Court.