Peachtree City
sewer officials have agreed to perform preventive maintenance for a small
sewer system in Tyrone in exchange for $600 a month from the town to cover
expenses.
The city's
Water and Sewerage Authority approved a contract with Tyrone officials
to perform the service at its meeting Tuesday night. The agreement means
WASA will periodically check the two pump stations in Tyrone's system,
which was designed to serve a 292-home subdivision, some commercial parcels
and a possible office complex.
Tyrone officials
initially resisted the sewer project until the developer, John Wieland
Homes, won a court ruling. The system will pipe the flow to Fairburn for
treatment; no treatment plant will be built in Tyrone and the limit each
day is 250,000 gallons.
WASA General
Manager Larry Turner said he didn't think the preventive maintenance checks
would overburden employees, since Tyrone's system is just five minutes
away from the northernmost pump station in Peachtree City. But if it does
get too unwieldy in the future, an escape clause is built into the contract,
Turner noted.
That clause
allows either party to terminate the contract upon 90 days notice.
Turner said
he calculated the $600 a month figure using the hourly pay for the highest-paid
employee who would inspect the Tyrone system, adding 35 percent to that
to cover fringe benefits.
The contract
calls for that price to be revisied Oct. 1 of each year to "reflect
actual labor costs."
Turner said
since the system is new, there should be relatively few problems with
it. But if there are, Tyrone has the option to contract with WASA for
the work or seek another source for the repairs.
If there is
an emergency with the sewer system, WASA will assist Tyrone if asked,
but Tyrone must pay the authority's actual labor and costs, plus fringe
benefits and all out of pocket expenses, the contract states.
WASA Attorney
Mark Oldenburg said the contract was written to specifically deliniate
what services the authority would be responsible for.
WASA member
Mike Harman said he thought the contract should include a fee schedule
for the "extra" work Tyrone might want WASA to perform in the
future. But he was reminded that Tyrone officials had already signed the
contract and the authority has been discussing this issue for several
months.
The contract
was approved 4-1 with Harman voting against it.