It will be another little while
before Peachtree City residents will have more answers about the Fayette
County Water System's plans to dredge Lake Peachtree.
City officials have agreed
to allow the use of Drake Field for staging equipment in the project,
which will remove an estimated 22,000 cubic yards of sediment from certain
areas on the bottom of the lake.
But water officials have decided
to hold a wide-open bidding process. Instead of pre-selecting a method
and seeking contractors to perform the job that way, the system will seek
bids from contractors, who will specify in the bid which method of removal
will occur.
"That way we'll have the
best price and the best plans for the county," said Jim Mallett,
the consulting engineer for the Fayette County Water System. "...
We'll look at all the prices and methods."
The city's input was the original
holdup, but now the water system has to wait for a permit from the Georgia
Department of Transportation. That's because the city wants the contractors
to access Drake Field by paving a road off Ga. Highway 54 at a cut-through
for the property.
The city contends the cut-through
will keep heavy trucks from mingling with residents who have business
at nearby City Hall and the library.
But for the county, it means
an estimated 30 additional days in time that will be needed to secure
the DOT's approval for the project.
"We're working on the
drawings for this right now," Mallett told the county's water committee
at its meeting last week.
Several committee members have
said they hope to avoid a dredging procedure that calls for reducing the
level of Lake Peachtree. Some residents are urging the county to use a
barging process that would allow trucks to take away the silt before it
dries out.
The dredging is required by
a contract with the water sys tem and the city since the water system
uses Lake Peachtree as a reservoir.