The construction
of taxiways and concrete pads for new hangars at Falcon Field is essentially
complete, though almost a full month behind schedule.
Because the
project was 29 days late, the contractor, Cline Service Corporation, will
have to pay up to $21,750 in liquidated damages. That figure hasn't been
finalized as airport officials await a letter from Cline representatives
indicating why the construction was delayed.
At Wednesday
night's regular meeting of the Airport Authority, Airport Manager Jim
Savage said the contractor "did not present any extenuating circumstances
that we believe would warrant a time extension" at a meeting last
week.
Cline was originally
given five months to complete the project, which was to have been completed
March 6. The final completion date was determined to be April 4, Savage
noted.
The new hangar
area has been designated for commercial use, with the authority charging
higher lease rates there to make sure the six hangar sites aren't used
for aircraft storage. The authority is trying to attract corporate jet
operations to locate there in addition to maintenance operators.