The town of
Tyrone is asking the Peachtree City Water and Sewer Authority to consider
maintaining its fledgling sewer system.
At its regular
meeting Monday night, the authority agreed to let Turner negotiate with
Tyrone officials about the request.
Turner told
The Citizen Tuesday that there are several concerns that need to be addressed
about such an arrangement.
"Obviously,
our system has to come first," Turner said, adding that it's also
important for the authority's expenses to be covered and for liability
issues to be settled. The authority also needs a way to get out of the
deal should the workload increase if Tyrone's sewer system expands in
the future.
Tyrone Town
Manager Barry Amos said the city hopes to avoid hiring additional personnel
to maintain the sewer system if WASA agrees to perform the work for Tyrone.
Amos said the
city expects the system will require little maintenance.
"We are
very pleased that WASA is willing to consider our request for assistance,"
Amos said.
Tyrone officials
initially resisted the idea of having a sewer system but developer John
Wieland Homes won a lawsuit allowing sewer service for a 292-home subdivision,
some commercial parcels and a possible office complex.
The Fayette
County Commission later filed a lawsuit seeking to stop Wieland's sewer
plans, which involve pumping the sewage to Fairburn for treatment. But
the litigation failed to derail the plan.
The maximum
sewage capacity available for the system is 250,000 gallons. John Wieland
Homes will eventually turn the sewer system over to the city.
The "sewer
system" in Tyrone won't have a treatment plant, but it does have
two pump stations, and that's why Tyrone officials want WASA to help maintain
the system, Turner said.