A large mixed-use
development will occur in northwest Coweta County, but it will not be
what the developers originally wanted.
During last
week's County Commission meeting, the commissioners passed a number of
motions concerning a 71 acre tract at the intersection of Ga. Highway
154 and U.S. 29 that Trivue wants to develop.
The series
of motions, sponsored by Commissioner Leigh Sclumper, allow the developers
to build a shopping center, townhomes and office space at the site.
Nearly all
the motions passed by a 3-2 vote with commissioners Nernon "Mutt"
Hunter and Jim McGuffey opposing the rezonings.
Both Hunter
and McGuffey wondered what impact the development would have on the watershed
area for the county's B.T., Brown Reservoir, which will be up and running
in the next two-three years.
McGuffey stated
that he voted in opposition because the EPD has given Coweta County a
letter of concurrence, not a permit, based on the present zoning. He stated
that he felt that Coweta County endangers the possibility of receiving
a permit for operation of the B. T. Brown Reservoir.
Several conditions
were attached to the approval of the zoning including:
·Performing
a Traffic Study to determine the design as required by the DOT. Entrance
connections to US 29 comply with the rules and regulations of the Georgia
Department of Transportation, and written approval from the DOT is submitted
to the county prior to issuance of a development permit.
·Taking
into consideration in development of the proposed site the lack of right-of-way
along U.S. 29 and agree to negotiate in good faith for any additional
right-of-way in accordance with future road improvements and widening
at a cost, if any, to be negotiated at the time of conveyance.
·Doing
site improvements, such as architectural standards, streets, parking,
landscaping,landscape berms, buffers, storm water detention that meet
the county's development standards.
·Ensuring
the development is served by a Georgia E-P-D- and Coweta County approved
sanitary sewer system and public water approved by the Water and Sewer
Department.
·Implementing
additional storm water detention, wetlands protection and erosion control
measures to insure adequate protection of the Alexander Creek drainage
basin .