With less than
three weeks to go until its latest deadline for expansion of its sewer
system, the Senoia City Council received a surprise Monday.
City Attorney
Drew Whalen informed the council that another 25 easements would have
to be obtained before the system expansion could be put out to bid.
The city is
getting ready to embark on building phase two of its municipal sewer system.
The price tag for the project is pegged at $6.1 million.
The city is
building the project with a combination of loans and grants and is still
working on permits, along with getting easements from residents to run
sewer lines through their yards.
It's the easements
that are causing city officials the most grief right now.
"Is there
somebody that can be held accountable for this? I'm frustrated that the
string seems to be getting longer," said Councilman Bill Wood.
Whalen said
some the new easements are a result of having to slightly shift the lines
to avoid a piece of property, but said the city's engineer, Ben Turnipseed,
is the one who is ultimately responsible for the plans.
The city wanted
to get the project bid out by April, but Whalen said the city is probably
going to have to ask for another extension of the grant approval from
the state Rural Development Department.
Construction
time on the project is pegged at one year. Councilman Bob Hannah said
the city might start having to look at condemnation to obtain some of
the easements.
Additionally,
Mayor Dianne Cleveland said she wants to receive an explanation from the
engineer on the new easements.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…