A future project to extend
TDK Boulevard into Coweta County via a bridge over Line Creek was originally
envisioned as a way to free up traffic on Ga. Highway 54 West by rerouting
employees to the city's industrial park.
But Peachtree City Mayor Steve
Brown is worried that Coweta officials may allow rampant development of
the area and create more of a traffic problem than a traffic solution.
The city is depending on funding
from the Georgia Department of Transportation for the project. But Brown
said in a recent letter that he agreed with Coweta officials that the
funds could be about 10 years away. Because of that the project "is
a moot point anyway," Brown told The Citizen Monday.
Brown said he wants more priority
to be given to the widening of Ga. Highway 74 south since large industries
located to Peachtree City "based on that unfulfilled promise."
"I have always been concerned
about what happens on the other end," Brown told council at its retreat
Friday, referring to how the area would develop in Coweta County.
At the retreat, Brown said
he is uncomfortable with the response from Coweta County Commissioner
Mutt Hunter, who told him the county would worry about planning its development
for that area once the extension came closer to fruition.
"At our meeting, he was
very noncommittal," Brown said, adding that he wanted to encourage
the development of a master plan for the area.
"We don't have any control
over what happens on the other side," noted Councilman Dan Tennant.
"There will be some development along there."
Across the creek in Coweta,
Hunter said the county's position has not changed on the extension of
the road. His biggest issue is funding, which has become tight at DOT.
Hunter also disputes concerns
about development in the area.
"That's not a concern
of theirs. It's far easier to build something in Peachtree City than Coweta
County," Hunter added.
The Coweta commissioner added
the meeting was held because the Coweta County Commission had heard that
Brown opposed the road extension during his recent mayoral campaign.
"There's no sense pushing
for something if the other side doesn't want it," he said.
Currently, the project is in
the design phase but a problem has cropped up relating to the location
of the bridge and the location of a spillway for the proposed Lake McIntosh
reservoir that Fayette County officials plan to build. The reservoir is
expected to boost water production by 8 million gallons a day.
Design for the road extension
project, which is between 85 and 90 percent complete, awaits a final
decision on the bridge location, according to Peachtree City Engineer
Troy Besseche.
The city has $460,000 built into its 2004 budget for preliminary work
on the project.