Under discussion for more than
two decades, Lake McIntosh is moving closer to becoming a reality.
The final linchpin in Fayette's
long-term plans to provide drinking water to local residents, the 650-acre
lake on Line Creek in southwestern Peachtree City is expected to boost
water production by 8 million gallons a day.
Engineers for the project last
week presented the county Water Committee a hydraulic report on the dam
that will create the lake, and the committee discussed three construction
options with estimated price tags ranging from $2.75 million to $8.17
million.
Plans are to discuss those
options with the city of Peachtree City before deciding which option to
take. The city's plans to extend TDK Boulevard will be affected because,
under the two least expensive plans, the road will run across the spillway
for the dam, which might flood the road during extremely heavy rains.
Under the most expensive option,
the spillway would be constructed directly on top of the dam, and the
road would cross Line Creek farther south, avoiding the spillway altogether.
State safe dam regulations
require that, under that option, the spillway be built high enough to
hold back the most severe flooding predictable, and the extra expense
would be mostly due to the requirement for more concrete, said engineer
Jim Mallett.
Committee member George Patton
suggested the city might want to participate in the cost in order to get
the county to fund the more expensive option. "We ought to talk to
them about participating with us because it benefits them and the county
both," he said.
Engineers will get input from
Peachtree City and the Water Committee will continue its discussion later.
Meanwhile, application for
a federal permit for the dam will be ready "soon," Mallett predicted.
Once the application is submitted, the process takes about a year, he
said, including several public hearings.
Final cost of the project will
be affected by the permit process, through which the U.S. Army Corps of
Engineers determines how many acres of wetlands the county will have to
create or restore in order to replace the wetlands lost by creating Lake
McIntosh.
Plans were well underway to
build the lake in the early 1980s, but were set aside in the face of opposition
from nearby land owners, mostly in Coweta County. That opposition has
since evaporated.
Back
to News Home Page |







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…