Senoia's City
Council got a crash course Tuesday afternoon of the cost in being in the
sewerage business.
The city is
getting ready to embark on building phase two of its municipal sewer system.
The price tag for the project is pegged at $6.1 million, but Rural Development
Fund representative Joyner Smith said time is of the essence in moving
the project forward.
The city is
building the project with a combination of loans and grants. Rural Development
is loaning the city nearly $3.5 million, and the city learned its monthly
payback on the 40-year note will be over $17,000.
Smith said
the payback on the loan will start one year after the construction is
complete. The city will have to pay a one time interest payment of $170,000
and then start making its monthly payments.
Smith said
the city must have enough in its sewer fund to pay the payment, and if
it doesn't, it would have to adjust sewer rates to make up the difference.
The city is
still working on permits for the project, along with getting easements
from residents to run sewer lines through their yards.
He urged the
city to get the work done as quickly as possible, because the current
soft economy could work in the city's favor when it puts the project out
to bid.
"Hopefully,
there will be some hungry contractors out there," he said.
If the project
can be bid by April, Smith said construction could start in late summer.
With a timeline of one year, the city could be fully hooked up to the
system by the summer of 2003, he said.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…