Local residents
can expect an increase on their sewer bills in the near future to help
pay for a $15 million project to expand the capacity of Peachtree City's
sewer system.
Currently,
the increase on the average residential customer is predicted to be around
$4 to $4.50, said Larry Turner, general manager of the Peachtree City
Water and Sewer Authority.
The authority
will also consider restructuring the fees charged to industrial and commercial
customers "to make sure they are paying for the share of services
they receive," Turner said.
The fee increases,
expected to take affect sometime in January, will bring the fees in line
with fees charged throughout metro Atlanta, Turner said. Currently, the
average monthly residential sewer bill is approximately $24.50, based
on the $3.50 charge per 1,000 gallons.
Some metro
area sewer systems have average bills upwards of $45 monthly, Turner pointed
out. The last time sewer rates were increased was in 1992, before the
city took over the sewer system, Turner said.
The $15 million
project will be financed over 20 years, and the funds from the increased
fees will be used to pay down that debt. The Peachtree City Council has
agreed to back the loan, which allows the authority to get a lower interest
rate by about one-half percent, Turner noted.
Once completed,
the expansion will increase the city's ability to treat sewage from 4.9
million gallons a day to six million gallons a day.
Part of the
expansion will double the capacity of the Rockaway wastewater treatment
plant from two to four million gallons a day. It will also add another
filtration system to the process there, which will result in better water
quality at discharge, Turner said.
Those same
filters will also be installed at the Line Creek waste water treatment
plant as part of the urban reuse program, which will put the water through
the special filters so it can be used to irrigate local golf courses.
Included in that program will be storage tanks so the specially-treated
water can be stored on days when it is not needed due to rainfall.
The expansion
project includes the decommissioning of the Flat Creek waste water treatment
facility, which has been operating for 35 years but was originally designed
to serve on a temporary basis, Turner noted. Because of its age, Flat
Creek costs more to operate than the other two plants.
The authority
plans to continue discharging the allowed .9 million gallons per day into
Flat Creek, however. In addition to maintaining that discharge capacity,
that move will also help maintain wetlands in the area, one reason why
the Southern Conservation Trust asked WASA to maintain the discharge there.
The discharge
for Flat Creek will be pumped in from the Line Creek facility, Turner
said.
Also included
in the expansion is the construction of a new administration/maintenance
facility at the Rockaway plant. Currently, WASA's administration and maintenance
complex is located at the to-be-closed Flat Creek plant.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…