It will be
at least next year before Senoia's Public Works Department has a new building
to call home.
In the latest
tangle between Mayor Joan Trammell and new City Council members, the council
voted Monday night to postpone awarding a bid to build the facility until
at least January.
The dispute
started two weeks ago when Councilman Bill Wood said he was not comfortable
with the bidding process involved for a new public works building.
Trammell and
City Administrator Leonard Thompson had recommended accepting a low bid
of $81,000 for the project. The project is a ready-built metal building
that will have the insides finished by city and county workers.
But in looking
over the bids, Wood said that only one company submitted a bid for the
stripped down project and he needed more time to examine the bids.
Monday, Wood
said he still had a problem with the bids, which sent Trammell into a
tirade.
"You need
to write down exactly what you want and submit it to (city administrator)
Thompson. Otherwise, I won't allow anything to be done until the end of
the year," she said.
Wood said he
was fine with waiting on the project, and Councilman Robert Belisle motioned
that new bids should be conducted after the first of the year. The motion
passed 4-1 with Trammell voting against it.
She apologized
to Public Works Director Bobby Hogan for the delay in the project and
said the council was cutting down all the work the city staff had done
in obtaining the bids.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…