An advisory
committee studying development of the West Village area is recommending
a slate of cart path system expansions and design elements totalling more
than $6.5 million.
Those projects
are listed in a draft of a plan compiled by city staff after multiple
meetings of the committee. The report also includes plans for access roads
to the north and south of Ga. Highway 54 which will be constructed by
developers.
Once the plan
is approved by the committee and the City Council, the report will be
filed with the Atlanta Regional Commission so the projects may be considered
for grant funding.
The ARC is
particularly interested in funding projects that encourage use of alternate
transportation. One such form of transportation the plan focuses on is
the city's existing cart path system and how it can be expanded to serve
new commercial and residential developments in the West Village area.
The plan also
briefly addresses a potential site for a commuter rail station should
the state begin operating a planned commuter rail line from Senoia to
Atlanta. The controversial topic was the subject of much debate initially,
but the committee eventually decided the best place to locate such a station
was in the Clover Reach area south of The Avenue at Peachtree City.
The committee
decided it wanted the rail station in a location where it would have a
local draw instead of a regional draw.
The rail station,
however, is not tabulated in the final list of projects recommended by
the committee with the exception of a cart path bridge which would be
built near the location in 2006.
Instead, the
main focus of the plan is on improvements to and the extension of the
city's cart path system which collectively total more than $3.5 million.
Those improvements
include $1.05 million for a path bridge over the railroad tracks adjacent
to Hwy. 54 and tunnels under the railroad bridge to provide access to
the eastern side of the area, including the Marketplace and The Avenue
at Peachtree City retail centers. The tunnels would connect to the bridge
in a unique cloverleaf design since the tunnels and bridge would be located
at significantly different elevations.
Another path
bridge is planned to cross Hwy. 54 near MacDuff Parkway; the bridge could
be designed as part of a scenic entrance to Peachtree City. Two path tunnels
are also included in the plan one for Hwy. 74 to link the Marketplace
center to the Westpark Walk center and another at Paschal Road.
Another $2.9
million in the plan is dedicated for landscaping and aesthetic enhancements
such as the burying of overhead power lines and planting along the median
and right of way of Hwy. 54.
The project
also calls for 10-foot wide sidewalks along Hwy. 54 on the north and south
for pedestrians.
Although they
will be funded by developers, the plans also refer to the creation of
access roads which will be developed north and south of Hwy. 54 so local
traffic can avoid using the highway to get around Peachtree City.
The northern
access road will extend from MacDuff Parkway to the planned Home Depot/Wal-Mart
access road, eventually linking up with Huddleston Road across the current
site of Line Creek Baptist Church.
The southern
access road would extend from an undeveloped commercial parcel west of
the Days Inn to a proposed roundabout intersection at Planterra Way. The
plan also calls for the relocation of the entrance to the Planterra Ridge
subdivision.
Big-ticket projects on the
West Village "wish list"
$1.05 million
for a cart path bridge and tunnels for the railroad bridge on Hwy. 54
to connect the West Village to developments at the intersection of Hwys.
54 and 74 (estimated for funding in 2003).
$875,000 for
a cart path bridge over the railroad tracks at the possible location for
a commuter rail station in the Clover Reach area (2006).
$600,000 for
a cart path bridge across Hwy. 54 near MacDuff Parkway (2003).
$400,000 for
a cart path tunnel under Hwy. 74 at Paschal Road (2006).
$350,000 for
a cart path tunnel under Hwy. 74 to connect the Marketplace retail center
with Westpark Walk (2006).
$200,000 to
construct a roundabout at Planterra Way where it would connect with an
access road (2005).
$1.2 million
to bury overhead power lines along Hwy. 54 (2003 and 2004).
$600,000 for
plants and landscaping in the median and right of way along Hwy. 54 after
it is widened to four lanes (2004).