A project to
replace three sewage pump stations in Peachtree City is partially completed.
The only major
task remaining is the construction at pump station number one, which is
located off Ga. Highway 54 at Lake Peachtree. It's expected to be up and
running sometime in August ahead of schedule, said Larry Turner, general
manager of the Peachtree City Water and Sewage Authority.
Pump Station
8, which serves the Publix shopping center off Hwy. 54 East and Shiloh
Mobile Home Park, is already back in service, Turner said. And Pump Station
5, located off Flat Creek Road and serving a small residential area, is
expected to go on-line next week, he added.
The project
to replace the pump stations is $600,000. But putting in new equipment
turned out to be cheaper than refurbishing old equipment, Turner said.
Pump Station
1 will have a backup power generator once construction is complete. The
failures at that pump station in the past have been due to power failures,
so the generator should eliminate those problems, Turner said.
Pump station
number one is one of the largest stations in the system, serving the area
from the intersection of Hwys. 54 and 74 all the way up to the Aberdeen
Parkway.
The pump stations
needed to be replaced for a variety of reasons, including their age and
the fact they were small for the sewage capacity the system is handling
now, Turner said.
No one is likely
to notice the affects of the improvements, Turner said, "But it will
improve the reliability of the pump stations."