Instead of waiting for the
Wal-Mart/Home Depot developer to build road improvements for the Ga. Highway
54/74 intersection, the Peachtree City Council has approved funding five
short-term road improvements for the area.
Three of the five projects
are part of the traffic improvement plan which RAM Development is responsible
for building so the retail center can meet the guidelines of the city's
traffic ordinance. But the development agreement stipulating those projects
hasn't been signed yet.
Doug Dillard, an attorney for
RAM, said the firm will reimburse the city for any funds it spends on
those three projects, as long as the cost is within reason and if the
development is given a green light.
The project is currently awaiting
the final permits from the state Department of Transportation, Dillard
said. Once those are in hand, the development agreement can be signed
and the road improvement projects will be one of the first items RAM wants
completed, he added.
Despite Dillard's assurances,
Councilman Steve Rapson said council should prepare to spend money from
its contingency fund to pay for the projects.
"The issue is we're already
three weeks further down the road," Rapson said, referring to the
previous council meeting where no action was taken on the issue. Waiting
any longer to act would do a disservice to city residents who get stuck
in traffic there every day, he added.
If council is reimbursed for
the three projects by RAM, only $157,000 would come out of the contingency
fund for the other two projects, Rapson said. The estimated total for
all five projects is $432,000.
If the city performs the work,
a delay could be caused by the process of applying for DOT permits, said
City Manager Jim Basinger.
The projects, in priority order,
are:
The addition of a 250-foot
right turn lane off Hwy. 54 east onto Huddleston Drive, tabbed at $85,000.
The idea is to allow traffic headed into the industrial park to use Huddleston
as a route there, bypassing the 54/74 interchange, which becomes clogged
during rush hour.
The addition of a right turn
lane on Huddleston at that intersection for traffic heading eastbound
on Hwy. 54. The $187,000 project would make the signal switch for Huddleston
shorter, officials believe.
Extending the left turn lane
for southbound traffic on Hwy. 74 so more vehicles can turn onto Hwy.
54 heading east. That would cost an estimated $40,000.
Installing an additional right
turn lane for southbound traffic on Hwy. 74 so more vehicles can turn
onto Hwy. 54 heading west; the estimated cost is $150,000.
The addition of a second left
turn lane for northbound motorists on Hwy. 74 so they can head west on
Hwy. 54. That project is expected to cost $55,000.