Efforts to provide
drought relief to about 40 Fayette residents are running 11 days behind
schedule ... due to rain.
Late last year the
County Commission, following the recommendation of the Water Committee,
agreed to build additional water lines to help residents whose wells had
gone dry.
In emergency situations
in which wells dry up in areas where county water is not available, the
Water System offers a deal. The customers pay the cost of running water
lines to their homes that would be adequate to serve only those homes,
and the Water System picks up the cost of making those lines large enough
to serve future customers beyond the trouble spot.
Water system director
Tony Parrott reported last week to the Water Committee that four of the
eight projects have been completed, and four remain.
But recent heavy rains
have slowed the construction.
Rains also have filled
the county's reservoirs, and water conservation efforts also are paying
off, said Parrott. Average daily production of water in April was 8.2
million gallons, compared to 11.4 million during April 2000, Parrott reported.
The county remains
on odd-even watering restrictions, with outdoor watering allowed 10 p.m.
to 10 a.m. on the appropriate days.
In other business
at last week's meeting, the committee voted to ask commissioners to approve
bidding out air conditioning for a pump house at Lake Horton. The project
is expected to cost $40,000 to $60,000, said Parrott.
Bids for fences to
protect two water tanks under construction as well as a wetland property
on Brooks Creek also received committee approval, and the group voted
to recommend that the county put money in its 2002 budget to paint a small
water tank in Peachtree City.
Recommendations to
the commission will be considered at the group's May 10 meeting, 7 p.m.
at the County Administrative Complex.