Extending TDK
Boulevard into Coweta County in the future would divert an estimated 1,600
vehicles a day from traveling into Peachtree City on Ga. Highway 54 West,
officials estimate.
According to
traffic forecasts, that would reduce traffic on Hwy. 54 in Peachtree City
by 20 percent.
But the extension,
which would include a bridge to cross Line Creek, also calls for four-foot-wide
bicycle lanes on either side of the road to allow for alternative forms
of transportation also.
Plans call
for the 2.46-mile road to connect TDK Boulevard to McIntosh Trail in Coweta
County. The bike path would likely be most utilized by residents in that
area, since the Peachtree City portion of the project begins in the industrial
park.
McIntosh Trail
is currently a collector roadway that, along with Stallings Road, provides
a secondary route between Sharpsburg and Senoia.
Transportation
officials predict that traffic volume on Hwy. 54 West in Peachtree City
will swell to 8,000 vehicles per day by the time the new roadway is opened.
No timeline for construction has been set.
The success
of diverting traffic from Coweta County to the industrial park will largely
depend on signage to alert drivers that the road will provide a shortcut
to the park, and it will also depend on the amount of congestion on Hwy.
54, officials believe.
The new two-lane
roadway will have 12-foot lanes for automobiles in addition to the lanes
reserved for bicycles. The proposed right-of-way for Peachtree City will
be set at 80 feet and the right-of-way in Coweta County will be set at
100 feet.
The speed limit
on the Coweta side will be 45 mph while the Peachtree City portion will
be rated at 30 mph.
The project
is a joint venture between Peachtree City and Coweta County. Once completed,
it is expected to provide an alternative route to the industrial park
for numerous workers there who actually reside in Coweta County and Newnan.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…