Coweta County
wants parameters established before it starts running emergency water
lines.
During Tuesday's
meeting, the board heard from water director Harry Hughes who suggested
the board go ahead and bid out engineering work for potential emergency
water lines.
Hughes said
if the bid process was done early, the county could get on a "fast
track" and get water lines to people within three weeks.
While the Commissioners
agreed with Hughes' recommendation to go ahead and do the bid process,
they were concerned about what constituted an emergency water line.
"If we're
not careful, we're going to be running emergency water lines all throughout
this county," said Commissioner Vernon "Mutt" Hunter.
The other commissioners
agreed and asked Hughes to come up with some parameters, such as distance
from an existing water line, that would constitute emergencies.
Although the
drought that gripped the county during the summer has eased and many of
the reservoirs are nearly full, many wells throughout the county are still
drying up.
The commissioners
emphasized that they want to get water to the people who desperately need
it first, and want to make sure that the Water Department is clear on
prioritizing the water lines.