The Peachtree
City Water and Sewer Authority has approved a plan to begin the preliminary
design that would double the capacity of the Rockaway sewage treatment
facility.
At its meeting
Monday night, WASA approved spending up to $240,000 on the preliminary
design process for the expansion. Currently, the Rockaway plant can treat
two million gallons per day, but after the proposed expansion it will
be able to treat four million gallons per day.
The expansion
will not only help meet the city's future sewer needs, but it will also
allow the city to close its oldest sewage treatment facility which has
become expensive to operate, Turner added.
The authority
has already taken the first step toward getting permission from state
environmental regulators by performing a watershed assessment study, said
WASA General Manager Larry Turner.
After the preliminary
design is completed, which is expected to take six months, it must be
submitted to the EPD for approval, Turner said.
"Then
it depends on how long it takes them to issue the draft permit,"
Turner said.
After the EPD
approves the preliminary design, it should take another four months to
finish the final design, Turner said. It could be a year or more before
construction on the expansion actually begins, he added.
In other business,
the authority approved a $584,350 contract to replace three pump stations:
one by Lake Peachtree, one behind the Publix shopping center and one off
Stratford Court. The contract goes to Willow Construction, Inc. which
has performed work for the city before, Turner said.
Willow Construction
was the low bidder, with the next highest bid at over $617,000 and the
other three bids received were over $700,000 each.
The construction
will take approximately nine months although a pre-construction conference
is scheduled for next week, Turner said.
The authority
also approved the issuance of a credit card to be used by WASA staff for
purchases. Turner said the card would allow some supplies and other necessities
to be purchased at lower costs over the Internet as opposed to making
purchases in stores.
The card has
a $5,000 limit and would be paid off each month, Turner assured the authority.
The card would
also make it easier for employees to pick up items at stores that don't
like to deal with the purchase order process. The card would be checked
out by the employee and a receipt must be brought back with the purchase
when the card is turned back in, Turner said.
Turner also
briefed the authority on two permit violations at the Flat Creek plant
which were reported in September. He said the violations involved the
presence of ammonia, but so far there is no explanation as to how the
chemical showed up.
More tests
are being conducted by a private lab to see if the ammonia results were
due to a testing error, Turner added. The tests are conducted regularly