'Through lane'
at Huddleston Road must first be approved by state traffic engineer
MUNFORD
The proposed
"through lane" for Ga. Highway 54 West at Huddleston Road isn't
a done deal yet.
The through
lane concept was hailed as the main factor in deciding the planned Wal-Mart
Superstore could meet the city's traffic ordinance. The City Council voted
3-2 to approve the concept plan for the Wal-Mart based on that decision,
but the final say on the through lane is out of council's hands.
The Georgia
Department of Transportation's state traffic engineer must sign off on
the concept before it can be built, said Keith Rohling, district traffic
operations engineer for the Thomaston district office.
"Usually,
with a design like this they'll look at it a little harder," Rohling
said, estimating it could take four weeks after the revised drawings are
received for a final decision from the DOT.
The revised
drawings for that plan haven't yet been received by the DOT, Rohling said
Wednesday morning.
The through
lane would allow westbound traffic on Hwy. 54 west to continuously flow
through the intersection instead of stopping at the traffic light at Huddleston
Road.
A concrete
island would separate the through lane from the current lane of traffic,
which would accept vehicles turning left off Huddleston Road onto Hwy.
54 west. Those two lanes would eventually merge into one lane before the
traffic would reach the bridge that crosses into Coweta County.
The stoplight
at the intersection would remain, but it would only affect the eastbound
traffic on Hwy. 54 and the traffic entering the highway from Huddleston
Road.
Rohling said
he was not familiar with a similarly designed traffic improvement anywhere
in Georgia.
"It's
not a conventional design, but it's not something I feel would be unsafe,"
Rohling said. "I felt like we could try it, but I don't know what
Atlanta's going to say."
For large developments
along state highways, the DOT typically receives recommendations from
a traffic engineer employed by the developer, Rohling said. The DOT then
studies that proposal, checks the numbers and sometimes negotiates with
the developer on how the final construction will be allowed, Rohling added.
At a council
meeting in October, Mayor Bob Lenox announced that the through lane concept
was what made the city's traffic consulting firm, Dames and Moore, change
its mind about the Wal-Mart Superstore's ability to meet the city's traffic
ordinance.
Until then,
Dames and Moore had contended that the Wal-Mart store couldn't meet the
traffic ordinance and therefore couldn't be built until the highway was
widened to four lanes.
The City Council
approved the concept plan 3-2, with Carol Fritz, Robert Brooks and Mayor
Lenox for approval and Annie McMenamin and Dan Tennant against. The action
came before a packed crowd at City Hall, many of whom spoke out against
the Wal-Mart plan being approved.
Several citizens
complained that the through lane concept couldn't work since the westbound
traffic on Hwy. 54 must be funneled through the bridge over the CSX railroad
tracks before it reaches the intersection of Huddleston Road.
RAM Development
has already secured DOT permits for other traffic improvements in the
area of the Wal-Mart/Home Depot project, including:
New turn lanes
in front of the Wal-Mart/Home Depot site;
Another turn
lane that will be added to the Hwy. 54/74 intersection to feed traffic
onto Hwy. 74 south;







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…