Peachtree City's
Water and Sewerage Authority will proceed with plans to increase sewer
capacity by expanding its sewage treatment facilities and beginning a
program to apply treated water to local golf courses.
WASA General
Manager Larry Turner presented the plans to the board at its meeting Monday
night. The expansion will allow the system to treat approximately 6 million
gallons of sewage per day, compared to the current maximum rate of 4.9
million gallons per day.
The city's
peak demand over the past year and a half has actually been lower, at
3.7 million gallons per day, Turner added.
But projections
are that WASA will eventually need to handle about 5.83 million gallons
per day, including all properties of Pathway Communities which currently
includes a planned subdivision that will be located partially in Peachtree
City and partially in unincorporated Fayette County.
Turner said
WASA has also been asked to provide sewer service to the potential school
site that will be located near that subdivision.
Turner was
asked if there have been any complaints about the proposed program to
apply the treated water at Braelinn and Planterra Ridge golf courses.
He said he hadn't heard any negative feedback.
"The golf
courses support this," Turner said. "They want it. It's a better
source of water than they're using now."
Such procedures
are commonplace in Florida and other areas that experience severe drought,
Turner pointed out. Florida has been doing golf course applications of
treated water for around 20 years, he said.
Plans are to
spread 1.1 million gallons per day of the treated water on the golf courses.
To store that water during periods of rain, a storage pond would likely
need to be built, Turner added.
An expansion
of the Rockaway sewage treatment plant will increase the sewer capacity
Eventually,
WASA plans to close its Flat Creek plant because it is costly to operate.
WASA would still maintain its discharge permit for Flat Creek, however,
so it can still release 900,000 gallons of treated sewage per day, Turner
added.
The expansion
plans must be approved by the state Environmental Protection Division
before WASA can proceed with the upgrade. Turner said the facilities plan
will be submitted to the EPD and WASA will move ahead with the design
development review process.