After nearly
two years of discussions, the city of Fairburn Monday approved a contract
to provide Tyrone sewer capacity.
"This
is a significant step," said Fairburn City Administrator Tony Cox.
Under the
agreement, Fairburn will provide Tyrone wastewater treatment capacity
through Fulton County until its new wastewater treatment plant is built.
The contract
stipulates that Tyrone can purchase 250,000 gallons of daily capacity
until the plant is built.
Tyrone will
pay Fairburn the wholesale rate that Fairburn pays Fulton County, plus
a 15 percent premium charge.
Fairburn
will supply Fulton County a $4 million performance bond to compensate
the county in case Fairburn does not build its own treatment facility.
Tyrone will split the cost of the bond.
After Fairburn
builds its plant, Tyrone will pay the city on a monthly basis, based
on Fairburn's operation and maintenance municipal rate.
Fairburn
is building the plant to provide sewerage to residents and businesses
to the east of U.S. Highway 29 to the the Tyrone town limits.
In order
to induce Fairburn to build the plant, Tyrone agrees to pay the city
for $570,000 within 30 days of completion of the contract.
Tyrone will
receive a cedit that will be pro-rated over the 30 years of the contract.
Tyrone will
be responsible for the installation of all gravity or pressure sewer
lines installed in unincorporated Fayette County, Fulton County, Fairburn
or Tyrone that is necessary to complete the agreement.
Tyrone will
be solely responsible for the maintenance and operation of the sewer
collection system.
If Fairburn
decides to expand its wastewater treament plant, it will notify Tyrone
and Tyrone will have the option of purchasing more capacity.
The contract
now moves to the Tyrone Town Council for its consideration.