this summer, something that has eluded the city of Senoia
for its entire history will be a reality.
City
Administrator Leonard Thompson said this week that final
modifications are being made on the first phase of the
city's sewer system. Residents in the city's low-income
housing will be the first to receive sewer service.
When the
sewer system starts up, a part of Senoia's past will
disappear as approximately 40 outdoor facilities will
fade from existence.
Several
years ago, the city received a $500,000 grant from the
state Department of Community Affairs to run the lines to
the lower income residents.
Now that
the lines are run, many in town are buzzing about a
tap-on fee, but Thompson explained that residents
shouldn't worry.
"Anybody
who lives here now will have 90 days to hook up. If they
wait any longer, it will cost them $1,500," he said.
The city is
offering the deal in order to get customers for the
system. Thompson explained that a lot of funding will
come from the new residents who move into town.
After phase
one is completed, the city will take bids for phase two
this October. The second phase will focus on getting
sewerage to the downtown area and local businesses.
He expects
the construction phase to last nearly two years, but said
that some areas will come on line earlier.
Developments
currently underway or planned will also have the option
to hook up to the system. A planned commercial
development in front of the Cumberland subdivision on Ga.
Highway 16 may choose sewer instead of septic, he said.
"It
might be cheaper for the developer to do that instead of
running all those septic tank lines," Thompson said.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…