Citing
"enormous pressure" from state officials, the
Coweta County commissioners have reaffirmed their
position on not talking about rezoning property until
public hearings are conducted.
The issue
came up after officials from the state Department of
Industry and Trade contacted the commissioners with a
prospect for the county's "mega-site" for
industrial development near Moreland. The prospect was
looking for some assurance that the site will be rezoned
for industrial use, but commissioners said they can't
discuss rezoning in advance.
The
1,200-acre site is one of five "mega-sites" the
state will use to encourage large manufacturing
operations to move their businesses to Georgia.
The site is
next to Interstate 85 at exit eight.
Tuesday
morning, the commissioners said they are all for economic
development, but they have rules to follow.
"Part
of this property is in my district. There's no reason for
the board to be pressured," said commission Chairman
Vernon "Mutt" Hunter.
Hunter
explained the board is forbidden to even discuss zonings
until public hearings are conducted.
"It's
not zoned industrial and wen't say anything about
it," he said.
The board
also asked county attorney Mitch Powell to ask the
attorney general for an opinion on the pressure the board
has received to talk about the issue.
Commissioner
Charlie Jones backed Hunter's statement up 100 percent.
"We
favor excellent jobs. This is the highest pressure. We're
not going to break the law," he said.
Hunter
added that if a mega-site project is good for the county,
he'll support it.
Scott
Frederick, director of 21st Century Coweta, told the
Coweta County Commission last month that the property
owners had agreed to let the property be listed as a
mega-site for industrial recruitment.
Mega-sites
typically draw companies such as automobile
manufacturers, and Frederick said Coweta's site has
everything that major industrial projects want.
"It's
close to an interstate, a municipal airport, a rail line
and is a short distance from Hartsfield International
Airport," said Frederick.
Typically,
large scale industrial companies look for 500-acre tracts
and Frederick said this site is even more attractive
because of the additional acreage.
Commission
Chairman "Mutt" Hunter thanked Frederick for
his presentation, but said this was only the first step
in having the property ready for an industrial project.
"The
land hasn't even been zoned industrial. All that's been
done is the land has been assembled," he said.
The
commissioners agreed at the April meeting that a
mega-site task force should be formed to keep the public
informed of issues such as environmental concerns,
traffic studies and economic impact.