As
expected, Monday night's Peachtree City Water and
Sewerage Authority meeting featured an update on the
ongoing watershed assessment along with a detailed
explanation of the permitting process for increasing the
system's capacity.
WASA
general manager Larry Turner reiterated his previous
statements that his department has no position one way or
the other on annexation or any similar issues, but he
must be prepared for whatever happens.
"There
is a misconception about how the water and sewer system
can dictate growth issues," he said. "We're no
different from Georgia Power - we're here to serve. And
when there is a demand, we must provide service."
Turner also
showed the board a videotape of a recent television news
report that pointed out the frequency of spills during
the recent winter storms and accompanying power outages.
According
to the WSB-TV story, a total of 31 spills and more than
600,000 gallons in the metro Atlanta area were attributed
to the weather of the past three weeks, and a spokesman
for the state's Environmental Protection Division was
quoted as saying that total was not all that harmful.
Turner said
he showed this to let the board see what his office sees
on a daily basis. A small spill into Lake Peachtree
within the last two weeks was the result of a power
failure at a pump station.
"This
is not a local problem or a state problem," said
Turner. "This is a national problem."
As for
spills that occurred during 1999, Turner reported that he
has received no comment so far from the EPD about its
consent order and the city's response.
While no
actual permit application has been made, the authority
has been investigating what would be necessary to get
approval for increased capacity and just how much would
eventually be needed. Turner said a few weeks ago that no
matter the outcome of the recent annexation debate,
during which the City Council voted to continue its
annexation moratorium, the sewer system would need to be
increased somewhat.
An
application is now being processed that would renew the
city's current permit, as is required every five years.
The current allotment is 4.9 million gallons per day, and
the system's average flow is about 3.6 mgd.
A study of
the city's possible future needs yielded the following
estimates of how the flow could rise:
� Current requested industrial use
- 0.4 mgd.
� Future industrial growth - 0.4
mgd.
� Future commercial growth - 0.1
mgd.
� Residential buildout - 0.5 mgd.
� Replacement of existing septic tanks
- 0.3 mgd.
� West Village use - 0.5 mgd.
That adds
up to 5.8 mgd, including the West Village, whose
annexation was most recently discussed. If all of those
categories are considered at once, Turner said, the
requested figure sent to EPD would be rounded up to six
mgd for planning purposes.
Turner
stressed that the system cannot be extended outside the
current service area without City Council approval. As
for annexation, "I think they've [council] been very
strong in their stance," Turner said, citing the
most recent vote.
Turner also
pointed out that the septic tank total takes into account
every single tank in the city, and many of those may not
need to be replaced for a long time.
But when
deciding what the flow amount should eventually be for a
permit application, "a lot of money is
involved," Turner said. If a request is sent in and
then the city decides in the future to go back and ask
for more, the extra flow capacity may not be there.
Turner will
send a letter to the City Council asking for some
direction. His current recommendation is not to consider
the proposed West Village in future plans, but he
repeated that it might be difficult to change that later.
The process
has taken some two years to get to where it is now, which
is the midst of the watershed assessment. After that is
completed, there will be public hearings to consider the
findings.
If any
application is made for expansion, the completion of the
process is probably three years away, Turner said.
As for the
watershed assessment itself, Turner addressed recent
public statements which he said insinuated that the
project was not being done correctly. He named several of
the key people involved in the study, pointing out their
credentials and qualifications to perform the work as
mandated by the state.
Turner said
that the public's accessibility to the details of the
watershed assessment had also been called into question.
In response to that, he laid out the timetable the
project has followed over the past year:
l At the May 4, 1999 regular WASA
meeting, the watershed assessment was discussed and
Turner pointed out the need for a watershed advisory
group.
l The advisory group met Sept. 1 in a
public meeting that was posted outside City Hall, which
is the city's normal procedure, Turner said.
l The Nov. 1 regular WASA meeting
included an update on watershed assessment.
l WASA officials met Jan. 5 with EPD
representatives, who Turner said were pleased and
satisfied with the city's progress.
l Another advisory group meeting was
held Jan. 11, and that meeting was also posted.
Turner
showed the board a number of documents from the federal
Environmental Protection Agency and other groups that say
the methods being used in the watershed assessment are
"clearly accepted."
Asked by
the board about the possible time frame for the next step
in the process, after the watershed assessment is
completed, Turner said he hopes to go to the EPD by this
fall, but that part could take more than a year.