Q. 5: See attachment No. 1
Q. 6: There are four
options available for financing this project. Two of the
options require a referendum and two do not. However, no
decision has been made as to which option will be
selected.
Q. 7: Only the newly
acquired acreage has been appraised. The original 33
acres has not recently been appraised. Therefore, we have
not established the current value of the combined parcel.
If you still do not have
all the information you need after Thursday evening's
hearing, we will be happy to provide you with any
information you would like, provided we know the answer
at the time.
Harold Bost, Chairman
Herb Frady, Commissioner
Attachment No. 1
A. Jail Expansion
1. Site work, including
Security Systems - $1,745,000
2. New Jail Construction
(139,661 square feet) - $15,177,190
3. Renovate Courthouse for
Sheriff Administration (23,000 sq.ft.) - $1,745,700
4. Renovate Existing Jail
Facilities for Storage (10,000 sq.ft.) - $677,875
5. Contractor's Overhead
& Profit @ 15% - 2,901,865
6. Escalation (avg.) @ 4.5%
- $1,001,143
Sub-Total Construction
- $23,248,773
7. Miscellaneous &
Contingencies @10% - 2,368,227
8. F.F.&E @ 2.75%
- $639,000
9. Project Management Fee @
2% - $520,000
10. Design Fees @ 4.5%
- $1,181,500
11. Design Services During
Construction @ 1.5% - $393,800
12. Testing &
Geotechnical Services @ 0.75% - $174,350
13. Legal &
Administration @ 0.75% - 174,350
Total Estimated Cost Jail
Expansion - $$28,7000,000
Note: 1. Construction costs
taken from estimate dated 4/20/99 prepared for the
Facilities Justice Group by Castell Marks International,
Inc.
B. Judicial Center
1. Site Work
a. earthwork & grading
- $200,000
b. utilities -
$250,000
c. drives & parking
pavement (116,000 S.Y.) - $1,160,000
d. storm water &
retention - $100,000
e. landscaping &
erosion control - $50,000
Sub-Total - $1,760,000
2. Finished Building
Construction (100,000 sq.ft.@ $125) - $12,500,000
3. Unfinished Building
Construction (50,000 sq.ft. @ $75) - $3,750,000
4. Escalation (avg.) @ 4.5%
- $810,450
5. F.F.&E.@ 4% -
$752,800
6. Miscellaneous &
Contingencies @ 10% - $1,981,325
7. Construction &
Project Management Fee @ 2% - $430,600
8. Design Fees @ 4.5%
- $968,875
9. Design Services During
Construction @ 1.5% - $322,950
10. Testing &
Geotechnical Services @ 0.75% - $161,500
11. Legal &
Administrative @ 0.75% - $161,500
Total Estimated Judicial
Center Cost - $23,600,000
Gerald Stoner
Fayetteville






Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…