The long
debate over paving Dogwood Trail near an industrial site
in Tyrone got a kick-start during Wednesday night's
council meeting.
The town
voted to fund $19,000 toward getting the road completed,
but added that industrial tenant MDT would have to get
busy on building the road.
The
discussion started early this year, when MDT, which
manufactures large umbrellas, asked the council to
relocate the roadway through its property for better
access. The company wants to build three warehouses and
agreed to rezone the northern part of the property
residential if the town would realign the road.
In
February, the town's Planning Commission supported MDT's
plan with four stipulations:
F MDT would request rezoning of the
northern part of its property to R-4, which allows a
one-acre minimum residential lot.
F The company would impose a 100-feet
buffer on any industrial property that borders
residential land.
F Any costs for paving Dogwood Trail
not funded by the Georgia Department of Transportation
would be borne by MDT.
F Construction of the road would begin
within four months.
In March,
the Town Council approved the plan, but nine months
later, work has not started on the road.
The latest
hold-up appears to be DOT's pledge to fund $41,000 on the
project. The cost of the project is $60,000, which leaves
$19,000 unfunded.
Wednesday
night, council members expressed their frustration at the
lack of progress on the road.
"I'm a
little fed up. It's time we do something," said
Councilman Paul Letourneau.
Councilman
Ronnie Cannon suggested the town go ahead and fund the
$19,000 and try to get the money back from MDT at a later
date.
"We're
just trying to insure the quality of life for everyone in
Tyrone," he said.
As part of
the motion, the council also specified that work on the
road must start before Feb. 15.