Fayette and
Coweta County officials will continue to meet with state
transportation officials to iron out the details of an
agreement reached last week that would hasten the
widening of Ga. Highway 54 west of Peachtree City.
County
commissioners last month formally alerted the Atlanta
Regional Commission and state Department of
Transportation that ARC's 25-year transportation plan
didn't place the Hwy. 54 project high enough on the
priority list to suit local officials.
It's the
number one priority locally, said the commission, and the
Coweta County Commission and Peachtree City Council added
their voices to that chorus.
Two weeks
ago, a delegation that included Fayette County Commission
Chairman Harold Bost, Peachtree City Mayor Bob Lenox and
Coweta County Commissioner Vernon "Mutt" Hunter
met with state officials and secured an agreement to
schedule the project for 2005, five years earlier than
the proposed Regional Transportation Plan had designated.
The RTP, if
approved by ARC early next spring as planned, will guide
transportation construction in the Atlanta region through
2025. Approval of the plan by ARC and by the federal
Environmental Protection Agency would end a moratorium on
transportation projects that has been imposed by EPA
because of alleged poor air quality in the region.
"We
anticipate that as soon as the moratorium is lifted and
the transportation plan approved, they will start to move
ahead" with construction of the Hwy. 54 project,
Bost told The Citizen this week.
Officials
in the next week or so will talk with DOT engineers who
plan projects for the south metro area, Bost said, in an
attempt to get agreement that the first order of business
will be construction of a new, wider bridge over the
railroad tracks on 54 just west of Peachtree City.
Traffic
going from Peachtree City into Coweta County gets jammed
up as it crosses the bridge, Bost said, because that's
where the highway abruptly narrows from four lanes to
two. And as that traffic backs up, it creates a jam
throughout the intersection of 54 with state Highway 74.
"We
feel that if we can get that bottleneck relieved, it's
the single biggest problem," said Bost.
Bost gave
credit for working out the agreement with ARC and DOT to
Coweta County's Mutt Hunter. Hunter, Fayette's former
public works director, has long had a good working
relationship with state DOT Commissioner Wayne
Shackleford, Bost said.
"It's
on the fast track now," Bost said of the Hwy. 54
project. If officials had waited until the 25-year plan
was approved to push for the change, he added, "It
would have been much harder to get it done after
that."







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…