Line Creek
Parkway will be built according to city standards,
despite a request by the builder to deviate from the norm
just a bit.
Michael
Rossetti asked the City Council at its Dec. 2 meeting for
a variance to the paving standard for the road. He wanted
to increase the thickness of the gravel base by two
inches and reduce the thickness of the asphalt by about
an inch and a half.
Rossetti's
proposed specifications were in compliance with state
Department of Transportation requirements.
The overall
paving section would be increased by a half-inch under
Rossetti's proposal, but the increase would be in less
expensive base material, according to city staff.
Rossetti
had indicated that he would invest the savings in a
landscaped buffer between the parkway and the homes in
Wynnmeade, and without the variance he would be unable to
do much, if any, landscaping, city staff said.
At the
council meeting, Rossetti said that the city's standards
are "a little heavy," and that the foundation
is most important, like in a house. Therefore, the
increased base is the key, he reasoned.
Doug
McMurrain of RAM Development, who said his company is
paying for about 75 percent of the road project, told the
council that the variance boils down to a cost issue and
a practical issue.
The road
work was budgeted according to old standards, after
litigation involving property for the parkway was
settled, McMurrain said. The current paving standards for
Peachtree City were adopted in 1997.
Approving
the variance would allow the developer to save $50,000 on
the road and still meet state standards, McMurrain said.
The extra money would go into landscaping.
If the
variance is denied, McMurrain asked that city staff at
least be given the authority to make decisions of this
nature regarding future projects, which they were unable
to do in this case.
Robert
Brown, a Planterra Ridge resident and soon-to-be
alternate on the Planning Commission, said that the city
needs to be sure it has a good road, because the city
will be responsible for its upkeep long after it is
completed.
Councilman
Jim Pace said that he considered the state's standards to
be good, but he felt a variance was not appropriate in
this case. He did express the opinion that city staff
could have a bit more flexibility in this area.
The rest of
the council agreed, as Robert Brooks moved to deny the
variance and send the matter back to staff for further
review. The motion passed unanimously.
In other
business, the City Council approved a resolution entering
into an installment sale agreement with the Georgia
Municipal Association concerning the acquisition and
construction of the new police station.
Financing
for the $2.27 million project is being provided by First
Union Bank at a 5.27-percent interest rate over 15 years,
according to city staff records. The agreement and
accompanying resolution are required for the GMA's
participation in the project.
The
agreement was approved unanimously.
Michael
Harman was named to begin a five-year term on the Water
and Sewerage Authority beginning Jan. 1. Councilwoman
Annie McMenamin, who served on the selection committee
with Pace and city manager Jim Basinger, said the
qualifications of all five applicants were impressive,
and her motion to appoint Harman passed unanimously.
Two current
members of the Recreation Commission, John Connolly and
Jan Shannon-Zink, were reappointed for three-year terms,
with Tammy Pakulski named as an alternate. A committee
consisting of Basinger, McMenamin and Councilwoman Carol
Fritz recommended the three applicants.
McMenamin
said Connolly and Zink had proven themselves
"assets" to the city, and noted that Pakulski
was qualified to step in at anytime if necessary.
Her motion
to approve all three positions passed unanimously.