The Peachtree City
Recreation Commission approved an amended draft of a
seven-year Public Improvement Program at Monday's regular
monthly meeting, with some adjustments resulting from the
survey of local residents taken earlier this summer.
The citywide survey asked
residents to rank projects in the Recreation Master Plan
according to priority, so the city could see if any
warranted special funding such as from a bond referendum
or local option sales tax.
Acting on the belief that a
bond referendum would not be an appropriate course of
action for any new recreation projects at this time, the
commission incorporated some of its higher-priority
facility needs, such as a multipurpose rink, into the PIP
over the next several years.
Response to survey
questions about new sources of revenue to fund the
projects was lukewarm, commission members say. And
residents already are dealing with funding requests
coming from other sectors of the county, such as the
proposed special purpose local option sales tax for
schools that will be voted on this fall.
With all that, commission
members felt that making any major move such as a sales
tax or bond referendum would not be wise, especially
since failure at the ballot box would lead to a lengthy
wait before being able to try again.
This was agreed upon by the
commission in June, and staff was directed at that time
to redirect certain projects into the PIP, with special
emphasis placed on the rink. Some of these projects were
also covered briefly at the City Council's budget hearing
in July.
The first two phases of the
rink have been incorporated into the PIP for fiscal year
2000, at a cost of $275,000. Several other projects have
been added for 2001, including expansion of the Gathering
Place, a multipurpose lighted field at Kedron,
amphitheater improvements, and site master plans for the
Meade complex. Later phases of the rink also are listed
under the 2001 plan.
Later projects include
soccer fields with concession facilities, picnic areas at
Glenloch and McIntosh Trail, playgrounds, Riley sewer
improvements, and replacement of a swimming pool cover at
Kedron. All of those projects are scheduled for 2002 and
2003.
Major projects scheduled
for 2004 and 2005 include a gymnastics facility and two
indoor basketball courts. Four baseball fields currently
are slated for 2006.
<!--
-----------