Peachtree City is looking
at a major expansion and renovation project to meet
expected administrative facility needs through buildout,
and it could begin this week.
The City Council has been
advised by its staff to adopt a facilities plan that
includes the construction of a new police station along
with renovation of City Hall and the Public Works
building. The plan was to be considered at last night's
council meeting.
The $2.1 million plan is
one of three options discussed at last winter's city
retreat. Other possible plans include the expansion of
the Public Works building, which would allow a
reconfiguration of City Hall and the existing police
station, or adding 8,000 square feet to the northern end
of the City Hall/police complex. The Peachtree City
Police Department is now headquartered in the lower level
of City Hall.
Under the plan being
recommended, a new 14,000-sq. ft. police station would be
built on a 5.5-acre site between Ga. Highway 74 and the
Flat Creek wastewater treatment plant. That property was
purchased using funds from the fiscal 1999 budget and the
cost of the land is not included in the estimated cost of
the new facility.
This move would allow the
Building Department, Planning and Engineering to move
downstairs into the current police offices, after minor
reconfiguration of City Hall and the Public Works
building. City officials expect this move to meet the
space needs of every department, while keeping a
consolidated Developmental Services in a location readily
accessible to City Hall staff. The Building Department is
currently on McIntosh Trail next to Public Works.
The first option considered
- expanding the Public Works building - was
seen as only a temporary solution, with the Police
Department still looking at a future space problem
requiring either reconstruction of its present facility
or the addition of a satellite precinct office. The
Police Department prefers a single, centralized office.
The possible relocation of
Developmental Services to another facility also was
deemed a disadvantage due to lost access to City Hall.
The second option was
rejected because the city believes it does not adequately
address parking issues. Adding the Building Department
staff to the City Hall site without removing the Police
Department would worsen an already strained parking
situation. Adding parking spaces at Picnic Park, behind
the police station, would reduce that facility's
recreational amenities as well as its status as a buffer
between various developments.
City staff has recommended
that the Georgia Municipal Association Bricks and Mortar
Lease Program be used to finance the facilities project.
The entire estimated cost
under this plan is $2.14 million, including underwriting
and legal fees. This would amount to about $210,000 per
year for a 15-year lease.
The other financing option
explored by the city, general obligation bonds, came out
at a slightly higher total - $2.2 million for the
project, or $212,000 in annual debt service.
The main difference between
the two plans is that the bonds would require a
referendum, while the GMA program would not require voter
approval. This would allow the city to move forward more
quickly, provided the facilities plan is approved.
"Based on the fact
that many of the city's administrative facilities are
already cramped and overcrowded, the sooner this project
can move forward the better," according to the
staff's written proposal.
<!--
-----------







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…